Friday, July 13, 2018

July Construction Update


Hi everyone! Here’s an update on our progress at the Hotel Peter & Paul (2317 Burgundy St). 

ACCOMPLISHED
Site work is complete (sidewalks, planting beds, parking lot, fence)
Interior/exterior painting
Kitchen equipment install
Masonry repair
Church interior plaster restoration
Restoration of original wood floors and trim

ONGOING
Landscaping, irrigation, site lighting
Rectory bar millwork and lobby check-in desk are under construction uptown
Developing menu for rectory bar
Actively seeking a General Manager!
3rd floor stage mural
Website – teaser is up at www.hotelpeterandpaul.com
Repair and reupholstering of antique furniture

UPCOMING
Furniture / art install
Hiring/training staff

Construction is winding down - we have removed all the temporary fencing, but still have a few months of work before our anticipated opening this fall. Anyone who wants to have a look inside, I gladly give tours, please email me at nathalie.jordi@gmail.com. 



View from the sleeping loft in room 313

Ann Marie Auricchio hand-painting the room numbers 

Transom, front doors and marble tile installed in school lobby

2nd floor corridor, original wainscoting

Church facade - masonry restored and window trim repainted

Wednesday, May 16, 2018

May Construction Update


Hi everyone! Here’s the update on our progress at the Hotel Peter & Paul (we finally picked a name – tried a bunch and decided none were as good as the original!)  

ACCOMPLISHED
Site work is nearly complete (sidewalks, planting beds, parking lot, fence)
School front doors installed
Masonry restoration complete
Interior painting nearly complete  
Tile and wood floor installation nearly complete

ONGOING
Elevator install
Rectory bar millwork and lobby check-in desk are being constructed uptown
Church interior plaster restoration
Repainting church façade – 1st try color came out strange so doing over
Developing F&B offering in ground floor of rectory
Actively seeking a General Manager!

UPCOMING
3rd floor stage mural
Branding, website
Kitchen equipment install
Arrival at the Port of a 40-foot container of European antiques we bought that will be repaired, rewired, reupholstered etc
Landscaping and site lighting

We’ll be a stop on the FMIA Home Tour this Sunday, May 20, from 12-4 pm. Only the church will be open (disclaimer, it is still very much under construction), but please come by and say hi. If you want a deeper dive another time, I very willingly give tours, email me at nathalie.jordi@gmail.com.

We still anticipate opening this fall. Thank you for your patience as we approach the final stretch. Our nearby neighbors have been amazingly persevering and tolerant and we really appreciate it.

School doors installed according to 1899 Diboll & Owens drawings (transom glazing to come)
 Rectory courtyard brick work complete


 Side altars in the church getting cleaned


Convent façade repainted

Thursday, March 15, 2018

March Construction Update


Hi everyone! Wanted to give you an update on our progress at Sts. Peter & Paul.

ACCOMPLISHED
Poured most of the new concrete (driveways, curb cuts, ramps)
Moved field office into the school so construction trailers could be vacated and the remaining parts of the parking lot completed
Restoration of lobby plaster – looks so beautiful we decided to leave it unpainted
Installation of school doors and trim halfway done
Closing-in of school walls and ceilings everywhere but fourth floor
Restoration of proscenium in former auditorium
Primed walls on floors 1-3
Installed all skylights, shingling underway

ONGOING
Exterior masonry restoration – feels never ending but we are getting there
Installation of vintage bricks in rectory courtyard
Dealing with unpleasant structural surprises in rectory
Repainting church façade
Installation of siding on convent  

UPCOMING
Elevator install
Convent exterior paint
Church interior plaster restoration
Branding, website

We are about 70% complete and I imagine some people are becoming fatigued by the noise, dust and general inconvenience of living next to an enormous restoration project in a dense residential neighborhood. As we enter the last quarter, we will most likely have half crews on Saturdays and a skeleton crew on site most Sundays. I am on site every day, so I know how intense it is, and although we spend a ton of time and effort trying to minimize impact, unfortunately we can’t entirely eliminate it. Please know that we are doing our best to work quickly and safely so we can turn the page and open our doors.  

If you want to see what we are up to, I am always happy to show people around, so email me at stpeterandpaulfeedback@gmail.com. Thanks again for your understanding as we push through the last few months. We still anticipate opening this fall.





















School facade restored























Arched shower in school




Brick install in rectory courtyard


























View from kitchen window