Monday, July 24, 2017

July Construction Update

Hi neighbors, Just wanted to give an update on what we’ve been working on this past month at 2317 Burgundy. For those new to the forum, this is the renovation of the former Catholic school/church campus into a hotel on Burgundy between Marigny & Mandeville. ACCOMPLISHED Plumbing, mechanical and electrical rough-in of ground floor Decking of 4th floor Grease trap installed Fire pump installed UPCOMING Structural framing of guest rooms in school Completion of north wall Starting electrical rough-in of rectory We are still on schedule with anticipated completion date of late summer/fall 2018. You can always reach me with any questions at stpeterandpaulfeedback@gmail.com or on my cell at 504.715.7142. Best Nathalie
Picture on left: view from 3rd floor. Right: windows off to get restored.