Hi everyone! Here’s an update on our progress at the Hotel
Peter & Paul (2317 Burgundy St).
ACCOMPLISHED
Site work is complete (sidewalks, planting beds, parking
lot, fence)
Interior/exterior painting
Kitchen equipment install
Masonry repair
Church interior plaster restoration
Restoration of original wood floors and trim
ONGOING
Landscaping, irrigation, site lighting
Rectory bar millwork and lobby check-in desk are under
construction uptown
Developing menu for rectory bar
Actively seeking a General Manager!
3rd floor stage mural
Website – teaser is up at www.hotelpeterandpaul.com
Repair and reupholstering of antique furniture
UPCOMING
Furniture / art install
Hiring/training staff
Construction is winding down - we have removed all the
temporary fencing, but still have a few months of work before our anticipated
opening this fall. Anyone who wants to have a look inside, I gladly give tours,
please email me at nathalie.jordi@gmail.com.
View from the sleeping loft in room 313
Ann Marie Auricchio hand-painting the room numbers
2nd floor corridor, original wainscoting
Church facade - masonry restored and window trim repainted